Installation of windows is now complete. Curtainwall installation is 95% complete and metal panel installation is 90% complete. Interior, mechanical, electrical, plumbing, and sprinkler finishes are ongoing throughout the building. Door and hardware installation has now begun. The kitchen and servery equipment are on-site and have been set in place. Gym equipment has now been installed. Elevator installation is set to be completed in early Spring.