The brick veneer installation is now complete, and the site crew has begun granite cheek wall installation at each of the building's existing entrances. Door hardware installation is now 90% completed, and all interior finishes are continuing to progress closer to completion. The elevator has been installed within the building and is awaiting finishes, adjustments, and inspection. The last curtain wall has been completed, and the roof parapet flashing work has resumed.