massive rebar grid laid out in the center part of the excavation site

Soil excavation to its final depth has been completed throughout each section. Rebar installation has begun in the center section on top of the mud mat. Mud mat placement has occurred on the West side. Rebar installation has begun on the West side. Formwork is ongoing in the center section to prepare for the next concrete pour on 4/8. Excavation for site utilities has begun on the front side of the project site.

 

Click here to see details of Lawrence Oliver for April 2023

Click here to see aerial footage of construction site for April 2023