crane lowering electrical transformer onto concrete foundation while workers guide it in place

National Grid set the transformer, connected the primaries, and installed the guy wires from the pole on Bruce St., crossing over to the pole on site. The final connection for the permanent power is awaiting the final rough electrical inspection, which is expected by mid-April. Two-thirds of the kindergarten floor area and the corridor were prepped over to the west side of the elevator. The installation of the divider strips, accessories, and terrazzo epoxy started.

 

Leahy March 2025 Update Progress Report

 